Task
- Arrange sea transportation of a mobile crane with total shipment weight over 2,300 tonnes.
- Ensure proper load distribution for 110 separate items of equipment.
Solution
- Chartered a vessel suitable for the heavy-lift project cargo.
- Developed engineering drawings and sea-fastening plans under the supervision of an engineering bureau.
- Coordinated loading/discharge operations and handled customs & shipping documentation.
Result
- The shipment of 110 items was delivered to Rotterdam successfully.
- Total weight: 2,300 t; total volume: 3,250 m³.
- All operations completed without delays or cargo damage.